GR01 · Construction planning
SKYi Greens · Tower 1, Wing A
Bavdhan, Pune · Tower 1
Activities
50
Critical activities
23
Project duration
356 days
Scheduled finish
05 Sept 27
Target finish · 2027-09-26
Activity schedule
| Activity | Task / location | Duration | Predecessors | Start | Finish | Float | Status |
|---|---|---|---|---|---|---|---|
| ●GR01-001 | Mobilisation & site survey Site / common areas · Pre-construction | 8d | — | 15 Sept 26 | 22 Sept 26 | 0 | Completed |
| ●GR01-002 | Design coordination Site / common areas · Design | 15d | GR01-001 FS+0 | 23 Sept 26 | 07 Oct 26 | 0 | Completed |
| ●GR01-003 | Approvals & permits Site / common areas · Approvals | 22d | GR01-002 FS+0 | 08 Oct 26 | 29 Oct 26 | 0 | Completed |
| ●GR01-004 | Excavation Site / common areas · Civil | 19d | GR01-003 FS+0 | 30 Oct 26 | 17 Nov 26 | 0 | Completed |
| ●GR01-005 | Foundation & waterproofing Site / common areas · Civil | 25d | GR01-004 FS+0 | 18 Nov 26 | 12 Dec 26 | 0 | In Progress |
| ●GR01-006 | Plinth completion Site / common areas · RCC | 16d | GR01-005 FS+0 | 13 Dec 26 | 28 Dec 26 | 0 | In Progress |
| ●GR01-007 | Floor 1 · RCC slab Floor 1 · RCC | 13d | GR01-006 FS+0 | 29 Dec 26 | 10 Jan 27 | 0 | In Progress |
| GR01-047 | Landscape & external works Site / common areas · Landscape | 26d | GR01-006 FS+0 | 29 Dec 26 | 23 Jan 27 | 195 | YTS - PAP |
| GR01-008 | Floor 1 · Blockwork Floor 1 · Masonry | 10d | GR01-007 SS+6 | 04 Jan 27 | 13 Jan 27 | 226 | In Progress |
| ●GR01-010 | Floor 2 · RCC slab Floor 2 · RCC | 13d | GR01-007 FS+0 | 11 Jan 27 | 23 Jan 27 | 0 | YTS - PAP |
| GR01-009 | Floor 1 · MEP first fix Floor 1 · MEP | 9d | GR01-008 FS+0 | 14 Jan 27 | 22 Jan 27 | 226 | In Progress |
| GR01-011 | Floor 2 · Blockwork Floor 2 · Masonry | 10d | GR01-010 SS+6 | 17 Jan 27 | 26 Jan 27 | 213 | YTS - PAP |
| ●GR01-013 | Floor 3 · RCC slab Floor 3 · RCC | 13d | GR01-010 FS+0 | 24 Jan 27 | 05 Feb 27 | 0 | YTS - PAP |
| GR01-012 | Floor 2 · MEP first fix Floor 2 · MEP | 9d | GR01-011 FS+0 | 27 Jan 27 | 04 Feb 27 | 213 | YTS - PAP |
| GR01-014 | Floor 3 · Blockwork Floor 3 · Masonry | 10d | GR01-013 SS+6 | 30 Jan 27 | 08 Feb 27 | 200 | YTS - PAP |
| ●GR01-016 | Floor 4 · RCC slab Floor 4 · RCC | 13d | GR01-013 FS+0 | 06 Feb 27 | 18 Feb 27 | 0 | YTS - PAP |
| GR01-015 | Floor 3 · MEP first fix Floor 3 · MEP | 9d | GR01-014 FS+0 | 09 Feb 27 | 17 Feb 27 | 200 | YTS - PAP |
| GR01-017 | Floor 4 · Blockwork Floor 4 · Masonry | 10d | GR01-016 SS+6 | 12 Feb 27 | 21 Feb 27 | 187 | YTS - PAP |
| ●GR01-019 | Floor 5 · RCC slab Floor 5 · RCC | 13d | GR01-016 FS+0 | 19 Feb 27 | 03 Mar 27 | 0 | YTS - PAP |
| GR01-018 | Floor 4 · MEP first fix Floor 4 · MEP | 9d | GR01-017 FS+0 | 22 Feb 27 | 02 Mar 27 | 187 | YTS - PAP |
| GR01-020 | Floor 5 · Blockwork Floor 5 · Masonry | 10d | GR01-019 SS+6 | 25 Feb 27 | 06 Mar 27 | 174 | YTS - PAP |
| ●GR01-022 | Floor 6 · RCC slab Floor 6 · RCC | 13d | GR01-019 FS+0 | 04 Mar 27 | 16 Mar 27 | 0 | YTS - PAP |
| GR01-021 | Floor 5 · MEP first fix Floor 5 · MEP | 9d | GR01-020 FS+0 | 07 Mar 27 | 15 Mar 27 | 174 | YTS - PAP |
| GR01-023 | Floor 6 · Blockwork Floor 6 · Masonry | 10d | GR01-022 SS+6 | 10 Mar 27 | 19 Mar 27 | 161 | YTS - PAP |
| ●GR01-025 | Floor 7 · RCC slab Floor 7 · RCC | 13d | GR01-022 FS+0 | 17 Mar 27 | 29 Mar 27 | 0 | YTS - PAP |
| GR01-024 | Floor 6 · MEP first fix Floor 6 · MEP | 9d | GR01-023 FS+0 | 20 Mar 27 | 28 Mar 27 | 161 | YTS - PAP |
| GR01-026 | Floor 7 · Blockwork Floor 7 · Masonry | 10d | GR01-025 SS+6 | 23 Mar 27 | 01 Apr 27 | 148 | YTS - PAP |
| ●GR01-028 | Floor 8 · RCC slab Floor 8 · RCC | 13d | GR01-025 FS+0 | 30 Mar 27 | 11 Apr 27 | 0 | YTS - PAP |
| GR01-027 | Floor 7 · MEP first fix Floor 7 · MEP | 9d | GR01-026 FS+0 | 02 Apr 27 | 10 Apr 27 | 148 | YTS - PAP |
| GR01-029 | Floor 8 · Blockwork Floor 8 · Masonry | 10d | GR01-028 SS+6 | 05 Apr 27 | 14 Apr 27 | 135 | YTS - PAP |
| ●GR01-031 | Floor 9 · RCC slab Floor 9 · RCC | 13d | GR01-028 FS+0 | 12 Apr 27 | 24 Apr 27 | 0 | YTS - PAP |
| GR01-030 | Floor 8 · MEP first fix Floor 8 · MEP | 9d | GR01-029 FS+0 | 15 Apr 27 | 23 Apr 27 | 135 | YTS - PAP |
| GR01-032 | Floor 9 · Blockwork Floor 9 · Masonry | 10d | GR01-031 SS+6 | 18 Apr 27 | 27 Apr 27 | 122 | YTS - PAP |
| ●GR01-034 | Floor 10 · RCC slab Floor 10 · RCC | 13d | GR01-031 FS+0 | 25 Apr 27 | 07 May 27 | 0 | YTS - PAP |
| GR01-033 | Floor 9 · MEP first fix Floor 9 · MEP | 9d | GR01-032 FS+0 | 28 Apr 27 | 06 May 27 | 122 | YTS - PAP |
| GR01-035 | Floor 10 · Blockwork Floor 10 · Masonry | 10d | GR01-034 SS+6 | 01 May 27 | 10 May 27 | 109 | YTS - PAP |
| ●GR01-037 | Floor 11 · RCC slab Floor 11 · RCC | 13d | GR01-034 FS+0 | 08 May 27 | 20 May 27 | 0 | YTS - PAP |
| GR01-036 | Floor 10 · MEP first fix Floor 10 · MEP | 9d | GR01-035 FS+0 | 11 May 27 | 19 May 27 | 109 | YTS - PAP |
| GR01-038 | Floor 11 · Blockwork Floor 11 · Masonry | 10d | GR01-037 SS+6 | 14 May 27 | 23 May 27 | 96 | YTS - PAP |
| ●GR01-040 | Floor 12 · RCC slab Floor 12 · RCC | 13d | GR01-037 FS+0 | 21 May 27 | 02 Jun 27 | 0 | YTS - PAP |
| GR01-039 | Floor 11 · MEP first fix Floor 11 · MEP | 9d | GR01-038 FS+0 | 24 May 27 | 01 Jun 27 | 96 | YTS - PAP |
| GR01-041 | Floor 12 · Blockwork Floor 12 · Masonry | 10d | GR01-040 SS+6 | 27 May 27 | 05 Jun 27 | 17 | YTS - PAP |
| ●GR01-044 | Facade & windows Site / common areas · Facade | 29d | GR01-040 FS+0 | 03 Jun 27 | 01 Jul 27 | 0 | YTS - PAP |
| GR01-042 | Floor 12 · MEP first fix Floor 12 · MEP | 9d | GR01-041 FS+0 | 06 Jun 27 | 14 Jun 27 | 17 | YTS - PAP |
| GR01-046 | Lifts & fire systems Site / common areas · MEP | 22d | GR01-041 FS+0 | 06 Jun 27 | 27 Jun 27 | 40 | YTS - PAP |
| GR01-043 | Roof waterproofing Site / common areas · Finishes | 15d | GR01-042 FS+0 | 15 Jun 27 | 29 Jun 27 | 38 | YTS - PAP |
| ●GR01-045 | Internal finishes Site / common areas · Finishes | 36d | GR01-042 FS+0, GR01-044 FS+0 | 02 Jul 27 | 06 Aug 27 | 0 | YTS - PAP |
| ●GR01-048 | Testing & commissioning Site / common areas · Handover | 15d | GR01-043 FS+0, GR01-045 FS+0, GR01-046 FS+0, GR01-047 FS+0 | 07 Aug 27 | 21 Aug 27 | 0 | YTS - PAP |
| ●GR01-049 | Occupancy inspection Site / common areas · Approvals | 11d | GR01-048 FS+0 | 22 Aug 27 | 01 Sept 27 | 0 | YTS - PAP |
| ●GR01-050 | Possession & handover Site / common areas · Handover | 4d | GR01-049 FS+0 | 02 Sept 27 | 05 Sept 27 | 0 | YTS - PAP |